2019.5.7
The modification project of Lenzing(Nanjing) was successfully put into production on May 7,2019.
This project was used to the transformation of the existing production line.It changed the the original “Blow Air Driver” to a traditional belt feeder. The project is complicated and time limited . Through the joint efforts of the engineers of Shanghai Agiland and Lenzing (Nanjing), new machines went into operation within 2 weeks, which meets the tight schedule. Two Agiland engineers guided the installation and commissioning, and has been acknowledged by our customers.
Lenzing(Nanjing) are very satisfied with the results. It fully demonstrates the reliability and efficiency of our project execution.